摘 要
给水系统采用分区供水,从市政管网上接一根DN80的引入管至消防水池以及生活水箱,六根引入管直供地下一层至地上设备层,四至十六层采用变频泵增压供水。四至八层为中区,九至十六层为高区。地下消防水池采用钢筋混凝土结构,置于地下泵房边,有效容积578.88立方米。建筑室内外排水均采用污、废水分流制,排水立管采用专用通气立管。地下室排水经排水沟汇集排至集水坑,经潜污泵提升排至检查井。雨水采用建筑内排水,选择重力半有压流系统,经屋面雨水斗收集后排入雨水管,通过雨水井排入市政雨水管网。
根据规范,该建筑为二类高层建筑,室外消火栓用水量20L/s,室内消火栓用水量30L/s,火灾延续时间2h。消火栓充实水柱高度13m,水龙带长度20m,水枪喷嘴流量1.33L/s,消防立管管径为DN100。
本工程的自动喷水灭火系统分十区,地下一层至三层由于有防火卷帘,设置三个防火分区,设备层至十六层,均两层设置一个分区。该建筑采用湿式自动喷水灭火系统,喷淋系统设计流量34.58L/s。报警阀设于地下泵房内,各层均设水流指示器、信号阀和末端试水装置,其信号均送入消防控制中心进行处理。选用消防增压稳压设备,屋顶水箱贮存火灾初期10min自动喷水灭火系统、室内消火栓系统用水量,初期灭火由水箱供水,后期灭火由地下室的消防水泵和喷淋泵供水。
关键词:给水系统,排水系统,雨水系统,消火栓系统,自动喷水灭火系统
Abstract
Water supply system using water rationing, from the municipal pipe network after the introduction of root DN80 tube to fire pool and water tank, life introduced six straight pipe for underground layer to the ground equipment, 4 to 16 layer adopts frequency conversion pressurized water supply pump.The four to eight floors are central, and the ninth to 16th floors are high.Reinforced concrete structure is used in underground fire pool in underground pump house, effective volume of 578.88 cubic meters .Adopt polluted waste water diversion system, building indoor and outdoor drainage riser drainage riser using special ventilation.The basement drain is collected into a water pit, and the drainage pump is hoisting up to inspect the well.The rainwater is used in the construction of drainage, and the gravity semi-pressure flow system is selected, and the rainwater pipe is collected in the rear of the roof, and the rain water is discharged into the municipal rainwater pipe network.
According to the specification, the building is a type 2 high-rise building, outdoor fire hydrant 20L/s, indoor fire hydrant water 30L/s, fire duration 2h.The hydrant has a height of 13m, the length of the hose is 20m, the nozzle of the nozzle is 1.33 L/s, and the pipe diameter of the fire riser is DN100.
The project of automatic sprinkler system (10, underground one to three layers with fire shutter, set up three fire partition, equipment to 16 layer, two layer set a partition.The building adopts a wet automatic sprinkler system with a design flow of 34.58 L/s.The alarm valve is set in the underground pump room, each layer is equipped with water flow indicator, signal valve and the end test water device. The signal is sent to the fire control center for processing.Choose fire pressurization voltage stabilizing device, the roof water tank storage fire early 10 min water automatic sprinkler system, indoor fire hydrant system, the early fire extinguishing by water tank water supply, the late fire from the basement of the fire pump and spray pump water supply.
Key words: Water supply system; Drainage system; Fire hydrant system; Automatic sprinkler systems; Rainwater system
目 录
第一章 设计任务 1
1.1总体要求 1
1.2设计基础资料 1
1.2.1建筑设计条件图 1
1.2.2相关资料 1
1.3设计主要内容 2
1.4应提交设计文件 3
第二章 建筑内部给水系统 4
2.1给水系统的分类和组成 4
2.1.1给水系统的分类 4
2.1.2给水系统组成 5
2.2给水方式选择 7
2.3给水管道的布置与敷设 9
2.4系统设计计算 10
2.4.1计算系统所需的水压 11
2.4.2计算系统所需的水量 11
2.2.3给水管网水力计算 13
2.5水泵选型 43
2.6贮水设备 43
第三章 建筑消防系统 45
3.1室内消火栓给水系统 45
3.1.1室内消火栓给水系统的类型 45
3.1.2室内消火栓系统的选择 48
3.1.3室内消火栓系统水力计算 49
3.2 自动喷水灭火系统 54
3.2.1自动喷水灭火系统的设置场所 54
3.2.2自动喷水灭火系统的类型 54
3.2.3自动喷水灭火系统组成及组件 54
3.2.4自动喷水灭火系统水力计算(作用面积法) 55
3.2.5选泵 56
3.2.6水泵接合器 56
第四章 建筑污废水排水系统 57
4.1排水系统的分类和组成 57
4.1.1排水系统的分类 57
4.1.2排水系统的组成 57
4.1.3排水系统的类型选择 58
4.2排水系统水力计算 58
4.2.1污水横支管水力计算 58
4.2.2污水立管水力计算 67
4.2.3废水横支管水力计算 68
4.2.4废水立管水力计算 76
第五章 建筑雨水排水系统 79
5.1屋面雨水排水方式 79
5.2降雨强度 79
5.3汇水面积 79
5.4设计秒流量 79
5.5雨水斗选用 80
5.6雨水连接管选用 80
5.7立管选用 80
参考文献 81
致 谢 82
第一章 设计任务
1.1总体要求
(1)要求完成《毕业设计设计任务书》中规定的全部内容;毕业设计成果(图纸及设计计算说明书)应在6月10日前提交;
(2)毕业设计图纸应符合相关国家标准设计规范和施工规范;图纸深度应符合或接近民用建筑工程给水排水施工图设计深度(04S901);